🚧 Construction Alert: Friday, June 12, 2026 🚧

In addition to the ongoing inside lane closures on Van Buren Boulevard, crews will implement temporary moving lane closures on Friday to complete asphalt paving work.

TRAFFIC IMPACTS
Friday, June 12
📍 Northbound Van Buren Boulevard at Rutile Street

7 a.m. to approximately 9 a.m.

🔸 Temporary closure of the northbound right-turn lane

🔸 No right turns from northbound Van Buren Boulevard to Rutile Street during this work

📍 Pedley Road and Jurupa Road intersection

Approximately 9 a.m. to 3:30 p.m.

🔸 Right-lane closures will shift throughout the intersection as needed while crews complete asphalt paving work

Ongoing traffic control:

🔸 Intermittent northbound and southbound inside lane closures remain in place on Van Buren Boulevard from 56th Street to Rutile Street during weekday work hours

✨ Businesses in the project area remain open and accessible.

Please plan ahead, allow extra time, and travel safely through the project area.

🗓️ The project is on track for completion in late 2027. For the latest updates:
Hotline: 800-679-9570
Website: www.JurupaGradeSeparation.com